Home › Guides › Reading quotes and costing a batch
Tooling, plates and setup: the one-time costs that set your first order size
One-off charges do not scale with your run, which is why a small batch costs so much per unit. What each one is, what it should cost, and how to get most of them to zero.
The reason a first batch costs so much per unit has almost nothing to do with the price of the ingredients. It is that three or four charges are levied once, whatever you make, and dividing them by a small number gives a big answer.
Understanding which of them you have to pay — and most first-time founders should pay none of them — is the cheapest improvement available to a first-run plan.
What each one is
| Charge | What you are buying | Rough scale | Recharged when |
|---|---|---|---|
| Injection mould | A steel tool for a custom container or closure | Thousands to tens of thousands | Never, if you own it |
| Printing plate or cylinder | One per colour, per component | Tens to low hundreds each | Artwork changes |
| Die or cutter | The shape of a label or carton | Low hundreds | Shape changes |
| Line setup | Changeover hours for a short run | Low hundreds to low thousands | Every run |
| Screen or pad print setup | Direct decoration on a container | Low hundreds per colour | Artwork changes |
The mould is the one that ends projects. A custom container shape is the most expensive decision available to a first-time founder, and it is almost always taken for aesthetic reasons at a stage when aesthetics are not what is failing. It also carries a second cost nobody mentions: a custom mould locks you to the supplier who holds it, unless ownership and transfer are written into the agreement — and they usually are not.
How much they distort a small run
Take $1,400 of plates and setup on a run of 3,000 units. That is $0.47 per unit, on top of everything else. At 6,000 units it is $0.23. At 20,000 it is $0.07.
This is the entire reason a supplier's price drops so steeply with quantity, and it is why asking for two quantities in your first email is the most informative thing you can do — the gap between them tells you how much of their cost is fixed, without anyone disclosing anything. The first email covers the phrasing.
Getting them to zero
- Take a stock component. A supplier's existing tube, jar or bottle has no mould to pay for. This single choice removes the largest one-off charge entirely, and stock does not mean generic — colour, decoration and cap change the look far more than shape does.
- Decorate with a label rather than the container. A printed label costs a plate or two; direct printing on the container costs a setup per colour and is far less forgiving of a design change.
- Cut the colour count. Plates are per colour, per component. A two-colour design on three components is six plates; the same design in one colour is three.
- Finalise artwork before plates are made. Plate charges recur on change, and first-time founders change artwork after seeing the first sample almost without exception. Budget for one revision rather than pretending there will be none.
- Ask for tooling to be amortised. Many suppliers will spread a mould charge across the first two or three orders instead of taking it up front. It costs them little and it fixes your cash problem.
The one you cannot avoid
Line setup is real work and somebody has to pay for it. The useful move is not to argue it away but to ask for it explicitly as a one-off fee, separate from the unit price. Suppliers respond well to this, because it is an honest answer to their actual problem — and once it is a visible line rather than a hidden loading on the unit price, you can see what your run size is really costing you. It is also frequently the way under a minimum: the five ways.
Where they belong in your costing
Put every one-off charge on a per-batch line, never a per-unit one. If you spread tooling into your unit cost and then change your run size, your whole cost model is quietly wrong — and it will be wrong in the optimistic direction, which is the direction that hurts. Our own costing keeps setup, testing and freight on a batch basis for exactly this reason: the seven lines.
Then check what else the quote left out — reading a quote line by line.
Batchkind keeps one-off costs on their own basis, so changing your run size re-costs the batch correctly instead of hiding the change.
Bring your quotes in